4-Lane Upgrade of Budhni–Shahganj NH-146B Corridor

The Construction work of 4-laning of Budhni to Shahganj bypass end (Package-III) of NH-146B from design km 73.750 to design km 102.000 involves upgrading a ~28.250 km stretch from Budhni to Shahganj bypass end into a modern 4-lane divided carriageway, with major and minor bridges, flyovers, VUPs, LVUPs, culverts, service roads, grade- separated intersections, and advanced safety systems, undertaken by NHAI to enhance corridor efficiency, reduce travel time, improve road safety, and promote socio-economic development across Sehore district and central Madhya Pradesh.

Project At Glance

ParticularsDetails/Status PKG – 3
 Length28.250 Km
 NH No.146 – B
 Project Cost Rs. 509 Crores
 ConcessionaireM/s Budhni Shahganj Highways Pvt. Ltd.
 Independent EngineerM/s Saptagon Asia Pvt. Ltd.
 Date of LOA16.03.2024
 Date of Agreement29.08.2024
 Appointed Date17.08.2025
Completion Date16.08.2027
 Construction Period730 Days
 Lane Configuration4 Lane
 Realignment2.050 Km.
 Bypasses19.890 Km (Budhni 16.440 Km + Shahganj 3.450 Km)
 Service Road/Slip Road21.230 Km (10.615 km LHS + 10.615 km RHS)
 R.C.C. Side Drain24.630 km (12.315 km LHS + 12.315 km RHS)
 Junctions27 nos. (Major – 1, Minor – 12, Grade Separated – 14)
 HPCTotal – 29 no. (New – 23 nos., Reconstruction 4 nos, Widening – 2 nos.)
 Box CulvertTotal – 28 nos.
 Culverts on Cross RoadTotal 26 (Box – 16 nos, HPC – 10 nos.)
 VOP1 nos.
 VUP5 nos. (Single Span 2 no. + Multi Span 3 no.)
 LVUP6 nos.
 Minor Bridge8 nos.
 Major Bridge4 nos.
 Toll plaza0
 Bus SheltersTotal 12 no. (6 (LHS) + 6 (RHS))
 Truck Lay Bye1 nos. (79+000 BHS) Including Toilet Block
 Way side amenities/Rest  Area1 nos. (91+300 RHS) (Only levelled & Graded and Boundary wall of 1.5 mtr. Height
 Fly over2 no. (83+775 & 87+540)
 ROB & RUB1 ROB Ch. 83+510 & 1 RUB Ch 80+905
 RE Wall18.928 Km (9.464 km LHS + 9.464 km RHS)
 Toe Wall3.230 Km (1.615 km LHS + 1.615 km RHS)
 Retaining Wall15.140 km (7.570 km LHS + 7.570 km RHS)
 Boundary WallEntire Length of Project at BHS

 

MonthRemarks
Aug 2025Preview PDF