BUDHNI TO SHAHGANJ 4- LANE ROAD UPGRADE

The Construction work of 4-laning of Budhni to Shahganj bypass end (Package-III) of NH-146B from design km 73.750 to design km 102.000 involves upgrading a ~28.250 km stretch from Budhni to Shahganj bypass end into a modern 4-lane divided carriageway, with major and minor bridges, flyovers, VUPs, LVUPs, culverts, service roads, grade- separated intersections, and advanced safety systems, undertaken by NHAI to enhance corridor efficiency, reduce travel time, improve road safety, and promote socio-economic development across Sehore district and central Madhya Pradesh.

Project At Glance

 Particulars Details/Status PKG – 3
 Length 28.250 Km
 NH No. 146 – B
 Project Cost Rs. 509 Crores
 Concessionaire M/s Budhni Shahganj Highways Pvt. Ltd.
 Independent Engineer M/s Saptagon Asia Pvt. Ltd.
 Date of LOA 16.03.2024
 Date of Agreement 29.08.2024
 Appointed Date 17.08.2025
 Completion Date 16.08.2027
 Construction Period 730 Days
 Lane Configuration 4 Lane
 Realignment 2.050 Km.
 Bypasses 19.890 Km (Budhni 16.440 Km + Shahganj 3.450 Km)
 Service Road/Slip Road 21.230 Km (10.615 km LHS + 10.615 km RHS)
 R.C.C. Side Drain 24.630 km (12.315 km LHS + 12.315 km RHS)
 Junctions 27 nos. (Major – 1, Minor – 12, Grade Separated – 14)
 HPC Total – 29 no. (New – 23 nos., Reconstruction 4 nos, Widening – 2 nos.)
 Box Culvert Total – 28 nos.
 Culverts on Cross Road Total 26 (Box – 16 nos, HPC – 10 nos.)
 VOP 1 nos.
 VUP 5 nos. (Single Span 2 no. + Multi Span 3 no.)
 LVUP 6 nos.
 Minor Bridge 8 nos.
 Major Bridge 4 nos.
 Bus Shelters Total 12 no. (6 (LHS) + 6 (RHS))
 Truck Lay Bye 1 nos. (79+000 BHS) Including Toilet Block
 Way side amenities/Rest  Area 1 nos. (91+300 RHS) (Only levelled & Graded and Boundary wall of 1.5 mtr. Height
 Fly over 2 no. (83+775 & 87+540)
 ROB & RUB 1 ROB Ch. 83+510 & 1 RUB Ch 80+905
 RE Wall 18.928 Km (9.464 km LHS + 9.464 km RHS)
 Toe Wall 3.230 Km (1.615 km LHS + 1.615 km RHS)
 Retaining Wall 15.140 km (7.570 km LHS + 7.570 km RHS)
 Boundary Wall Entire Length of Project at BHS
NO.MONTHREMARKS
1.Aug 2025Preview PDF
2.Sep 2025Preview PDF
3.Oct 2025Preview PDF
4.Nov 2025Preview PDF
5.Dec 2025Preview PDF
6.Jan 2026Preview PDF
7.Feb 2026Preview PDF